Power Station & Dip Seal Upgrades

HSE – No LTI’s, reportable injuries or incidents.

Scope of Work

  • In house fabrication of 3CR12 Dipseal and carbon steel draglink conveyor – all fabricated to tight tolerances over 24+ meter lengths
  • On site removal and disposal of Draglink conveyor and Dipseal using bespoke inhouse designed jacking and skating solutions to remove existing and install the new
  • Installation on site of both units 1 and 2
  • Removal and installation methodology designed by Sync Lift Engineering reduced the replacement duration by 5 days per unit